Experience :: Government :: Projects
Project: | RECOVERY – Utility Construction Carters Lake, Georgia |
Owner: | United States Corp of Engineers |
Project Location: | Murray County, Georgia | Completion Date | June 2011 |
Contract Value: | $ 662,097.79 |
The work consisted of utility construction that included water main and fiber optic conduit with cable and termination included. Meco installed 9250 linear feet of 1 1/4" HDPE water line, 2800 linear feet of 4" HDPE water line, directional boring with 4" casing. Work also included fiber optic conduit 11250 linear feet and fiber optic cable 12500 linear feet, directional boring 4" casing, and we were required to terminate and test all fiber optics.